CERC Approves 1.7 GW NHPC Solar Tariffs Ranging ₹2.43 to ₹2.47/kWh

⚡ Quick Read

  • What happened: The CERC has approved tariffs between ₹2.43/kWh and ₹2.47/kWh for NHPC’s 1,670 MW ISTS-connected solar projects, including a 500 MW greenshoe allocation.
  • Why it matters: The approval validates the use of greenshoe options in competitive bidding, setting a precedent for scaling capacity at the lowest discovered tariff.
  • Watch: Future regulatory clarity on the formal inclusion of greenshoe mechanisms within Ministry of Power bidding guidelines.

Background and Context

In October 2024, NHPC initiated a competitive bidding process for 1,200 MW of interstate transmission system (ISTS)-connected solar power projects. The tender attracted significant interest, with eight bidders participating in the process. The resulting tariffs were highly competitive, ranging from ₹2.43/kWh to ₹2.47/kWh. The initial allocation involved several major players, including Teerth Gopicon, Hanur Solar Power, ReNew Solar Power, and Avaada Energy. Bharat Petroleum Corporation was also initially involved but was subsequently disqualified for failing to meet the minimum capacity threshold of 50 MW, which adjusted the base allocation to 1,170 MW.

Key Details

NHPC exercised a greenshoe option to expand the project capacity, allocating an additional 500 MW to bidders willing to match the lowest discovered tariff of ₹2.43/kWh. Primary beneficiaries of this expansion included Hanur Solar Power and ReNew Solar Power. NHPC defended the use of the greenshoe mechanism before the Central Electricity Regulatory Commission (CERC), arguing that it enhances efficiency and economy in public procurement. Despite the lack of explicit mention of greenshoe options in standard Ministry of Power guidelines, NHPC maintained that the practice is not prohibited and aligns with the flexibility permitted under the request for selection (RfS) documents.

What This Means for EPCs and Developers

For EPC contractors and developers, this approval is a significant milestone. It confirms that regulatory bodies are willing to accept innovative capacity-scaling mechanisms if the bidding process remains transparent and the resulting tariffs are competitive. The discovered tariffs of ₹2.43/kWh to ₹2.47/kWh are notably lower than the ₹2.52/kWh to ₹3.05/kWh range seen in other recent commission-approved tenders, signaling a continued downward pressure on solar power pricing. Developers should note that strict adherence to technical and financial evaluation criteria—such as the minimum capacity threshold—remains critical to avoiding disqualification.

What Happens Next

While the CERC has approved these specific tariffs, the commission noted a lack of formal recognition for the greenshoe mechanism in current guidelines. Future tenders may see more explicit regulatory frameworks regarding how and when such options can be exercised. NHPC, having secured the necessary approvals, will now focus on project execution to meet the timelines associated with these ISTS-connected assets. Stakeholders should monitor upcoming Ministry of Power updates for potential formalization of the greenshoe mechanism in standard bidding documents.

📊 Key Data

NHPC’s 1.7 GW solar project tender has received regulatory approval for its discovered tariffs. Below is the summary of the auction details.

Attribute Details
Issuing Authority NHPC
Tender Reference Tranche IX
Capacity/Scope 1,670 MW (1,170 MW base + 500 MW greenshoe)
Technology Type ISTS-connected Solar
Project Location Not specified
Estimated Value Not specified
EMD/Bid Security Not specified
Bid Deadline October 2024
Pre-bid Meeting Not specified
Project Duration Not specified
Tariff Structure ₹2.43/kWh to ₹2.47/kWh
Eligibility Networth Not specified
Eligibility Experience Minimum 50 MW capacity threshold
Special Conditions Greenshoe option exercised